Community Hospital
- Location
- Dulwich
- Client
- Southwark Council
The project required the management of two separate working locations on the hospital grounds, s the hospital remained operational for the duration of the project.
Parcel 1 was previously demolished to underside of ground slab with all materials being processed and stockpiled. The scope of works to test, process and recycle all inherited stockpiles, utilising material for backfilling and pilling mat construction. Drainage diversion works were undertaken with a new drainage system installed across the site. A tarmacked haul road was installed to enable a new access to the site for the construction works.
Parcel 2 consisted of former hospital buildings that were derelict and required demolition. As the buildings had been empty for some time, they had become the home for bats. Working alongside an Ecologist, the bats were relocated before the asbestos removal and demolition work was undertaken. The site was located in close proximity to the railway line, residents and the hospital. Noise, dust and vibration monitors were implemented along with an Environmental Management Plan to assist with demolition and ensure the least amount of disruption possible.
Once the superstructure had been demolished the foundations, connective tunnels and obstructions were removed before a piling mat was constructed using recycled materials from site.
Scope of Works for Community Hospital
Parcel 1
- Processing and testing all inherited stockpiles on site
- Removal of discovered contaminated water
- Mass reduce level dig
- Drain diversion and installation of a new drainage system
- Backfill and installation of a piling mat
- Installation of a site access haul road
Parcel 2
- Asbestos removal
- Demolition Scaffold
- Hand demolition of the roof to enable the safe migrations of roosting bats
- High reach demolition
- Removal of all foundations and below ground obstructions
- Installation of piling mat